Straight Wall (Double Wythe Wall)
DoubleWytheTSection2v2.png
Exploded View
DoubleWytheTSection1v2.png
Assembly View
 
 
Step by Step
DoubleWytheTLayout.png
Step 1. Install the Layout units.
Note: You have several options:
Option A: You can utilize F-BIMs and b-BIMs to interlock one wall to the other enhancing the wall performance.
Option B: You can utilize straight BIMs instead of the F-BIM and b-BIM pair and keep both wall separated.
Option C: You can use utilize straight BIMs and intercalate the F-BIM and b-BIM.
DoubleWytheTLayer1Step1.png
Step 2. Install the first brick of Layer/Course 1 (a J-BIM in this case).
DoubleWytheTLayer1Step2.png
Step 3. Interlock the second brick.
Note: Press firmly down until the top surface of the block interlocking module (BIM) of the second brick is flush with the adjacent brick. You can also use a dual head rubber hammer (mallet) to carefully drive down the dovetail shaped legs of the new brick into their female counter parts.
DoubleWytheTLayer1Step3.png
Step 4. Finish Layer/Course 1.
DoubleWytheTLayer2Step1.png
Step 5. Install the first brick of Layer/Course 2.
DoubleWytheTSection1v2.png
Step 6. Finish Layer/Course 2.
 